Picture signing off on a thorough plan, then waiting months until anyone can use what it describes, while priorities shift underneath it. Once AI shrinks that waiting time, the old argument against planning needs rechecking.

Yes, AI gives software teams a strong reason to do more deliberate upfront planning. When implementation is faster, a good plan has less time to go out of date, and clear decisions start paying off sooner. Our approach is to pin down outcomes, constraints and acceptance criteria before every build that carries real consequences, and to leave assumptions open to whatever the evidence shows.

By upfront planning we mean settling decisions before the code is written. Waterfall, as a project-management method, arranges delivery as a sequence of phases. The first can be adopted without locking every requirement in place until the last release.

Research status: 10 November 2026. What follows is an argument built on primary research and a worked hypothetical. Devoun has not run its own experiment pitting waterfall against Agile, and the 100× coding scenario further down is an assumption rather than a measured industry figure.

Why is AI a reason to rethink upfront planning?

Once implementation is quick enough that open decisions take up most of the delivery time, the argument for planning first gets stronger. An agent can start on an agreed requirement straight away. But when no one has defined what correct means, fast implementation can just as quickly produce work that has to be thrown out or redone.

Take a customer export. Two agents could build the interface and the API at the same time. With a tenant boundary, schema and error contract already agreed, they converge on one result. Told only to “build the export,” each makes its own guesses about those choices.

Starting from the same uncertainty, a change users can try this week is less exposed to shifting circumstances than one that needs a year of implementation. Faster implementation can make planning pay better, even though it does nothing to make predictions perfect.

The wider change in engineering work is the subject of our essay on AI, specifications and the comeback of the software factory. This article is narrower: how much should be decided before the next build.

Did waterfall fail only because coding was slow?

Slow implementation was one route by which a waterfall plan went stale; finding problems late was another. Code delivered instantly can still meet the wrong requirement. So planning has to surface wrong assumptions before the team is heavily committed, and it has to allow decisions to change when the evidence does.

As early as 1970, Royce’s paper cautioned against finding system constraints only in late testing, and it described feedback flowing between development stages. That makes it a weak basis for defending a rigid one-pass process. Read the original large-system development paper.

The Agile Manifesto likewise sees value in plans, but ranks responding to change higher. Sticking to a plan once evidence has turned against it wastes effort, however fast the implementation.

Has AI already made implementation 100× faster?

Nothing in the studies reviewed here shows a general 100× gain in how fast software gets implemented. The outcome varies with the task, the developer, the tool and what is being measured. Time to finish a programming task, volume of code activity, number of releases and value to customers each answer a separate question.

EvidenceReported resultBoundary
Copilot controlled experiment, conducted in 2022Of 95 programmers recruited, those who finished with Copilot needed 55.8% less time.A single JavaScript HTTP-server task, not delivery of a whole product.
METR’s early-2025 experimentWith 16 experienced maintainers working 246 issues, having AI raised completion time by 19%.One particular repository setting and generation of tools, not a slowdown that holds everywhere today.
Writing Code vs. Shipping Code, September 2026 revisionLooking at more than 500,000 GitHub developers, this observational study found code activity grew far more than releases did.Counting output measures neither elapsed speed nor value to customers.

In its February 2026 follow-up, METR states that selection effects and the difficulty of timing concurrent agents leave its newer productivity estimate unreliable. Nor should the earlier slowdown be read as a judgment on current tools.

Still, 100× is worth treating as a thought experiment: suppose one piece of implementation really did get that much faster. How much faster would the project as a whole get?

How would 100× faster coding change a project?

In a made-up sequential project, coding 100× faster can turn planning into a bigger slice of delivery, while the overall speedup stays well short of 100×. How big the effect is depends on how much of the original time was implementation and whether other work speeds up as well. The arithmetic says nothing about the right planning budget.

Hold scope and acceptance standards constant, and take 10 elapsed days of planning, 80 of implementation and 10 of verification and release. Only implementation gets faster. The stages run one after another, and rework and queues stay the same. The inputs are for illustration; they are neither Devoun measurements nor industry averages.

Total days = 10 + 80 / implementation speed multiplier + 10

Implementation multiplierImplementation daysTotal daysSpeedup for the whole projectShare spent planning
1×801001×10%
10×8283.57×35.7%
100×0.820.84.81×48.1%
Implementation takes no time (the limit)0205×50%

At 100×, planning takes up almost half the timeline even though not a single day was added to it. The share grew only because implementation got smaller, which does not prove that a planning phase twice as long would be better.

To apply this to your own delivery, measure the critical path, and do not add up durations that run in parallel. Where AI also shifts testing, review or rework, estimate each of those effects on its own. What matters is the elapsed time until a change is accepted and usable.

Which decisions should be made before an agent starts?

Settle the decisions that would make a quick implementation costly to reverse: the outcome for the user, ownership, data boundaries, interfaces, what happens on failure, and acceptance criteria. Describe each one in enough detail to constrain the next build. Do not write up harmless implementation choices just because an agent is able to produce pages about them.

For changes with real consequences, put these questions to the responsible owner:

  • Outcome and scope: whose problem gets solved, how success will be visible, and which nearby requests are left out.
  • Constraints: what data and actions the system may touch, what it has to keep intact, and which compatibility promises are already in place.
  • Interfaces: what every component takes in, gives back and logs when something fails.
  • Acceptance and recovery: which evidence allows a release, who decides, and how a rollout that goes wrong is halted or recovered.

The April 2026 MirrorCode results from Epoch AI and METR show agents reimplementing a lot of software on their own when given executable reference behavior and detailed tests. That is a narrow benchmark. It backs the value of specifications that can be checked, but it proves neither that waterfall is better nor any measured multiplier on human speed.

A reviewer has almost nothing to verify in “Handle failures gracefully.” By contrast, “When a provider response is uncertain, keep the operation identifier and reconcile status before trying again” states behavior you can test.

How deep should planning go for a given change?

Base the depth on two things: how uncertain the requirement is and how costly the decision would be to undo. Requirements that are settled but have expensive consequences call for careful preparation. Behavior that is uncertain yet cheap to change calls for an early experiment. If both uncertainty and reversal cost are high, start by designing a safe way to learn that does not commit the whole system.

How uncertain the requirement isWhat reversing it costsBest next stepExample
LowLowAgree a brief acceptance contract, then build.A change to how something is displayed, with an agreed example and no change to stored data.
LowHighWork out dependencies, failure cases and recovery before anything runs.A migration that has to keep current records and integrations intact.
HighLowWrite down what you want to learn and try a throwaway version.Testing two onboarding flows with users who are representative.
HighHighBefore committing, cut the uncertainty with a simulation or an isolated trial.Trying a new allocation policy on synthetic data before it can touch real accounts.

When an agent can turn out a safe prototype fast, spending another week arguing over a speculative interface is often a bad trade. Quicker building can raise the payoff from planning around known constraints and lower the payoff from guessing preferences you could simply watch.

Count reversal cost broadly: the people affected, any data lost, commitments made, disruption to operations and engineering effort. Generating code cheaply does not make all of those consequences cheap. A hard security requirement is still a constraint, even if a spreadsheet makes the risky experiment look like it pays.

How do you know the plan is good enough to start?

You can stop planning once the next slice of implementation has an agreed outcome, explicit constraints, an owner who is responsible, acceptance criteria you can observe and a way to recover. Write down the uncertainties that remain and decide how each will be tested. Keep planning only if one more decision would likely save more avoidable loss than the time it takes to make.

Here is a synthetic example. A support agent has to request a full refund through a payment provider, and the eligibility and approval policy is assumed to be agreed already. Where those policies contradict each other, start with the separate guide on resolving conflicting business rules, before writing the specification.

Decided before implementationRequirement you can test
AuthorityThe approved refund can only be requested by an authorized support role, and only within its own tenant.
Operation identityStore a single stable idempotency key for the authorized refund, and use a provider that honors that key on every attempt.
ConcurrencyClicking at the same moment or receiving a message twice must not create two refund operations for one approved request.
Uncertain provider responseAfter a timeout, the operation waits for reconciliation. A lost response is not, by itself, a reason to start a new operation.
Acceptance and recoveryShow in a test environment that unauthorized requests are denied and that duplicates and lost responses are handled; document how operators reconcile an outcome that stays unresolved.

With that contract you can look into how the provider behaves and build a limited test integration. It does not amount to a refund system that is implemented or verified. Helper names are the agent’s choice; business rules are not, and neither is treating a timeout as proof that no money moved.

Ask what one more planning session could decide that this safe implementation would not reveal more cheaply. If the only thing left is polishing the document, begin the bounded build.

What does a plan-first AI delivery cycle look like?

In a plan-first AI delivery cycle, each piece of implementation stays small enough to review, and the specification stays easy to change. Agree a bounded change, build it, test it against acceptance criteria that were reviewed independently, and go over the result with its users or owner before starting the next build.

  1. Pick a single outcome. Name the user, the change you will be able to observe and who can accept it.
  2. Clear up ambiguity that would be costly. Go through the constraints and failure cases the planning matrix flagged.
  3. Produce an implementation someone can review. Divide the work along boundaries where behavior can be verified, and note anywhere it departs from the approved contract.
  4. Check both the code and the assumptions. Test that it is correct, read the diff and gather evidence that the behavior actually helps the user it is meant for.
  5. Revise the specification. Before another build begins, make the accepted behavior, the assumptions that were rejected and the next open question easy to see.

The Spec Kit introduction from GitHub talks about specifications that evolve and tasks small enough to review, and our Spec Kit production guide goes into the tooling. Even a well-structured specification needs someone independent to judge whether its assumptions hold.

DORA’s small-batch guidance stresses fast feedback for AI-assisted delivery as well. Size each batch by what you are able to verify, even if the agent could produce more.

How do you know if more planning is worth it?

Look at accepted delivery, rework and defects that escape to production. Time it from the moment clarification begins until a release is accepted, counting specification review and waiting time. Cutting coding time only helps if the work around it neither wipes out the gain nor lowers the bar for acceptance.

In a proposed pilot, take similar changes and run some with a short task brief and some with a more explicit upfront contract. Note the size, uncertainty, reversal cost, how familiar the team is with the area and the tool versions. Where you can, assign comparable tasks at random; where you cannot, treat the result as descriptive and keep the differences between tasks in view.

Measure elapsed lead time together with the human effort spent on planning, implementation and review. Note reopened work, defects found after release and whether the change delivered the outcome intended for users. These are measurements we propose, not findings from a pilot we have run.

Hold scope and quality criteria steady: counting generated lines rewards volume, and a rise in releases may only mean work was cut into smaller pieces. Project budgets are covered in our AI MVP cost guide. The question here is whether the extra clarification pays for its place in the cycle.

So should waterfall come back?

Bring serious upfront planning back wherever requirements can be made clear and mistakes would be costly to undo. AI makes that worth trying, since a well-specified implementation may now land while its assumptions still hold. Keep the scope bounded, change the plan as evidence comes in, and widen planning only if accepted delivery gets better.

With a workflow that is already understood, we would write a precise specification before giving it to agents. With a product whose users or value proposition are still unclear, we would plan the experiment and collect evidence early.

When your team still cannot agree on the outcome, the constraints or who owns acceptance, Devoun’s software discovery and requirements work is built for those decisions. Its scope is described in the guide to a software discovery phase. Our CoreMax Cloud platform stabilization case study gives related engineering context; it is not evidence of an AI speed multiplier or of how waterfall compares.

Bring one proposed change to a discovery conversation. Work out what has to be settled before implementation, and what evidence would let you release it.

FAQ on AI, Waterfall and Upfront Planning

Can AI write the specification, not just the code?
AI is useful for drafting a specification, spotting contradictions and suggesting failure cases. Settling the intended behavior is still a job for a person with authority over the product. Keep assumptions clearly apart from requirements that have been agreed, and get the acceptance criteria reviewed separately from the generated implementation. A well-written document can still describe the wrong product.
In an AI-assisted project, who should own acceptance?
Name whoever can accept the business outcome, plus the engineering reviewers who answer for technical constraints; each may decide on a different part of one change. Do not hand final acceptance to the agent that produced the work. Agree what evidence is required before implementation starts, so review does not turn into an argument about what was meant.
Does planning this way mean dropping Scrum?
The workflow we propose works without switching project-management frameworks. Within its existing cadence, a team can clarify the next change that carries consequences before building it, and review what it learned. Begin by improving the quality of decisions and of the evidence used for acceptance. Judge any change to meetings or roles by the delivery problem it is supposed to fix.
What if requirements change in the middle of implementation?
Stop the work that is affected, work out which approved decisions have changed, and check what that means for interfaces, data, tests and the release. Revise the specification together with the responsible owner before going on, and keep whatever work still fits. A changed requirement can be valuable evidence; insisting the earlier plan was right forever can turn it into rework that never needed to happen.
Is this about building AI products or about coding with AI?
It is about AI-assisted software development, where an agent helps build a product that might contain no AI at all. If the product itself uses a model, that model’s behavior also has to be evaluated in the setting it is meant for. Generating code faster proves neither that probabilistic outputs meet the product’s acceptance criteria nor that users want the feature being proposed.
Do specifications belong in the Git repository?
Keeping specifications versioned can make a change easier to review next to its reasoning and tests. Put them in the repository if the people who approve requirements can get to it and review there. If not, maintain an owned source somewhere else and link to the exact version. What you need is traceability and upkeep, and copying a document nobody maintains into Git gives you neither.

Build the product, not just the backlog

Facing a real product decision like the one in this article? Devoun can scope, build, harden or lead the software work, bringing senior judgment at founder level.

Service paths that fit:

Back
Atta Ur Rehman

11 min read · 10 Nov 2026
Last reviewed

Next